North Sheyenne Street Project

◄ Back
May 7, 2021

Construction Update - May 7, 2021

Road closures:
• Sheyenne Street is closed from north of Seventh Avenue W. to north of Fourth Avenue W.
• Traffic is detouring to Sukut Street for local access and Ninth Street E. for thru traffic between Main Avenue E. and 13th Avenue E.

Progress:
• Crews completed phase 1 storm sewer and pressure tested the new water main system.
• The temporary water system in phase 1 is scheduled to be removed early next week.
• Crews will prep Fourth, Fifth and Sixth Avenues W. for hand paving next week and expect to completely pave Fourth and Fifth Avenues W.
• Sheyenne Street in phase 1 is scheduled for paving in two weeks.

Schedule:
• Phase 1 is expected to be completed by the end of June.
• The project is currently on schedule for phase 1.

Closeup picture of road preparation for pavingFourth Avenue W. and Sheyenne Street road preparat Next Photo
Facebook Twitter Email