Sheyenne Street Segment 2 - Beaton Dr. to 32nd Ave

Sheyenne Street Segment 2 Finished Section Rendering

About this Project

Reconstruction of Sheyenne Street from Beaton Drive to 32nd Avenue to increase roadway capacity from one lane in each direction to three lanes in each direction. Includes installation of traffic signals at major intersections. The project coincides with I-94 interchange reconfiguration project.

Estimated Construction Cost

  • $24 million (partially funded by ND DOT)

Estimated Special Assessments

  • $2,000-$3,000 for residential properties with less than 2 acres
  • Assessment for costs associated with segments 2 and 3

Project Schedule

  • Estimated Start Date: June 2018
  • Estimated End Date: June 2020
  • Project completion: 95%

Road Closures

  • Current traffic pattern:
    • Open to two lanes of Sheyenne Street traffic in each direction north of 26th Avenue W. to Beaton Drive, including the use of both Sheyenne Diversion channel bridges.
    • Open to three lanes of Sheyenne Street traffic in each direction south of 26th Avenue W.
    • Temporary access in use at 21st Avenue W. and Sheyenne Street intersection with a dedicated southbound left-turn lane.
    • 24th Avenue W. and Sheyenne Street intersection is open to right-in/right-out traffic movements.
    • 32nd Avenue W. intersection is fully open to drivers. Local access will continue to use 32nd Avenue W. and Sheyenne Street intersection to travel south to side streets.
    • Sidewalks open for pedestrians south of 26th Avenue W. to 32nd Avenue W. intersection.

Completed Work

  • Lift station sheeting
  • Temporary pipe crossings

Current Work

  • Sanitary sewer force main at diversion channel
  • Water main relocations

Overview Map

WestFargo Segment2 Overview - Week of October 7