Goldenwood and Pinewood Area Street Overlay

Goldenwood and Pinewood Area Street Overlay map

About this Project

The purpose of the proposed project is to increase the lifespan of the existing streets. The need for the proposed project is warranted by the deteriorating conditions of the existing streets. 

Street Improvement District No. 2253 will involve milling, patching, leveling, overlaying, and other miscellaneous items.

Project Schedule

  • Estimated Start Date: May 2018
  • Estimated End Date: September 2018
  • Percent Complete: 0%

Completed Work

  • Saw cutting repair areas
  • Paving

Current Work

  • Seeding & mulch at replaced curb

Upcoming Work

  • Stabilization