Sheyenne Street Segment 2 - Beaton Dr. to 32nd Ave

Sheyenne Street Segment 2 Finished Section Rendering

About this Project

Reconstruction of Sheyenne Street from Beaton Drive to 32nd Avenue to increase roadway capacity from one lane in each direction to three lanes in each direction. Includes installation of traffic signals at major intersections. Project coincides with I-94 interchange reconfiguration project.

Estimated Construction Cost

  • $24 million (partially funded by ND DOT)

Estimated Special Assessments

Project Schedule

  • Estimated Start Date: June 2018
  • Estimated End Date: October 2018
  • Percent Complete: 0%

Road Closures

  • East- and westbound lanes adjacent to the medians on 32nd Avenue east and west of Sheyenne Street closed May 9-11
  • South lane of eastbound 32nd Avenue east and west of Sheyenne Street closed May 14-18
  • Road will be open to one lane of traffic in both directions with reduced lane size
  • Congestion and delays likely during peak traffic

Completed Work

  • Lift station sheeting
  • Temporary pipe crossings

Current Work

  • Lift station form & footings
  • Retaining wall footings & forms
  • Surveillance camera installation
  • Pole installation

Upcoming Work

  • Overhead power line removal
  • Box culvert work